Mining in southern and western Africa and oil and gas in the Gulf share a reliance on large motors, long cable runs and equipment that cannot afford unplanned downtime. Insulation testing is the cheapest way to find a failing motor or cable before it takes a production line with it. This guide covers how to set up a practical programme for those environments.

Why These Sites Are Demanding

Heavy motors run for long hours, often in heat, dust, moisture or corrosive atmospheres, and a failure can stop an entire process. Long cables to remote pumps and conveyors add leakage paths. Testing at planned intervals and trending the results turns a surprise failure into a scheduled repair.

Spot Readings and the Polarisation Index

A single one-minute reading is a quick screen. The polarisation index, the 10-minute reading divided by the 1-minute reading, is more revealing for larger machines because it separates good dry insulation from damp or contaminated insulation. Standards for rotating machines give minimum PI values, and a commonly cited figure for modern insulation classes is 2.0, but follow the standard and the manufacturer's guidance for your motor. Our Megger guide explains PI and DAR in detail.

Discharge after every test

Insulation under test stores charge like a capacitor. Large motors and long cables can hold a dangerous charge after the test. Discharge through the instrument's discharge path or a suitable resistor, and keep earthed for as long as the standard requires.

Choosing the Test Voltage

Test voltage should follow the rated voltage of the equipment, and standards give recommended levels by rating. Low-voltage motors are commonly tested at 500 V or 1000 V, while medium-voltage machines call for 2500 V or 5000 V. Using too low a voltage can hide defects, and too high can damage aged insulation. Read the motor insulation testing schedule and how to choose an insulation tester.

Cables and Long Runs

Test cables between phases and from each phase to earth, with both ends isolated. Long cables have high capacitance, so allow a longer charging time before reading and discharge fully afterwards. Compare each phase to its neighbours, since a single low phase is the clearest sign of a developing fault. For related tests, see continuity, insulation and contact resistance compared.

Instruments for This Work

For sustained PI tests in the field, the motor-driven CIE/777 range holds a steady voltage for as long as needed. These are available as single-range and multirange motorised and motor-cum-hand-driven versions, listed under motor-operated insulation testers. For battery-powered work, the DIT-5000 digital insulation tester offers 500 V, 1000 V, 2500 V and 5000 V output and readings to 200 GΩ, and the DIT-2500 adds DAR and PI calculation. Both are under digital insulation testers.

Building the Programme

  • List every critical motor and cable, with its rated voltage.
  • Set an interval by criticality and environment.
  • Test the same way each time and record temperature.
  • Correct to a reference temperature and trend the results.
  • Act on a falling trend, not just on a failed limit.

Tell us your motor ratings and site conditions and we will help you pick the right insulation testers.

Cambridge Instruments & Engg. Co. · Est. 1963
Looking for an instrument,
not just an answer?
Multimeters, clamp meters, insulation testers, earth testers - manufactured in Howrah, India. Pan-India supply.